Addendum review checklist for electrical bids

A late addendum is where good bids quietly break: the estimate was checked, then the documents changed. Work this list every time an addendum drops — especially inside the last 48 hours. Free, no sign-up.

Also free: the bid-day checklistThe pre-bid RFI template

1 · Read it like it costs you money (it does)

  • Read the addendum narrative AND every reissued sheet — the narrative rarely lists everything that changed on the drawings.
  • Build a one-line delta list as you read: sheet, what changed, estimate line affected. If a change has no estimate line, that's the finding.
  • Check which earlier addenda this one modifies or supersedes — addendum 3 quietly editing addendum 1 is a classic miss.
  • Confirm the bid date and time. Addenda move deadlines more often than estimators re-check them.

2 · The big-money reissues

  • Fixture schedule reissued? Re-count types that changed, confirm your lighting quote is against the NEW schedule revision, and get that in writing from the vendor.
  • One-line or riser reissued? Re-check gear ratings, breaker counts, feeder sizes and lengths against your gear quote and feeder takeoff.
  • Panel schedules reissued? Circuit counts move device and wire quantities — spot-check the panels with the most changes.
  • Specs reissued? Diff the Division 26/27/28 sections: basis-of-design swaps, added testing or commissioning, new submittals, warranty changes.
  • Site/civil sheets reissued? Re-check site lighting, pole bases, duct banks, and trenching ownership — scope boundaries move on addenda too.

3 · Quotes that just went stale

  • Every vendor/sub quote dated BEFORE the addendum: does it still match the documents? Their quote says 'per plans and specs' — which revision?
  • Lighting, gear, and fire alarm quotes are the usual casualties — confirm each against the addendum delta list, by email, before bid close.
  • A supplier who hasn't seen the addendum is pricing a different job. Forward it and ask for written confirmation or a revised number.

4 · The bid form, last

  • Acknowledge every addendum by number on the bid form — an unacknowledged addendum can make the bid non-responsive.
  • Re-read alternates and unit prices: addenda add, delete, and redefine them late. Price what the CURRENT bid form asks for.
  • If the addendum changed allowances or cash allowances, carry the new figure exactly as written.
  • Final pass: your qualifications letter — anything the addendum made ambiguous gets carried, RFI'd, or qualified in writing.

Addenda are exactly what re-reviews are for.

Upload the addendum and Bidprobe re-reviews the whole package against it — what changed, what it touches in your estimate, and the RFIs still worth sending. Re-reviews are included on every plan, and your first review is free. See a complete sample report.