The final pass before you sign the bid. Work top to bottom in the last 24 hours — every line is a real way electrical subs lose money after award. Free, no sign-up: read it here or take the printable PDF.

Download the PDFAlso free: the pre-bid RFI template

1 · Documents & addenda

  • Latest revision of every drawing confirmed against the drawing list — no superseded sheets in the takeoff.
  • Every addendum acknowledged on the bid form AND traced into the estimate (fixtures, gear, alternates, dates).
  • Addendum issued in the last 48 hours? Re-check the fixture schedule, one-line, and bid form line by line.
  • Specifications reviewed for Division 26, 27, 28 AND Division 0/1 (bonds, wages, schedule, liquidated damages).
  • Bid form complete: all alternates, unit prices, and allowances priced; acknowledgments signed.

2 · Scope boundaries (where the money leaks)

  • Site lighting, pole bases, and site conduit: on the civil sheets? Who owns them — you or the site contractor?
  • Division 27/28: who runs telecom conduit, pulls cable, terminates, tests? Who powers access control and cameras?
  • Fire alarm: your FA sub's exclusions vs what the spec assigns to Division 26/28 — elevator recall, HVAC shutdown, monitoring, verification/acceptance testing.
  • Mechanical equipment: starters, VFDs, interlocks, disconnects — schedule says Div 23, one-line says you. Which governs?
  • Utility scope: transformer pad, grounding grid, secondary conduit, metering, utility fees — carried or excluded in writing?
  • Temporary power, hoisting, firestopping of your penetrations, excavation/backfill for electrical — carried or excluded?

3 · Code basis

  • Enforced code edition NAMED in the spec/permit? If not — code-basis RFI, and note it in your qualifications.
  • Local amendments / AHJ quirks checked (or flagged to verify). The state/province answer is not always the answer.
  • Estimate built to the enforced edition, not the newest one (AFCI/GFCI/SPD/EVSE deltas move real money both ways).

4 · Money items

  • Bid bond + performance/payment bonds: required? Priced or in markup — shown to be SOMEWHERE.
  • Prevailing wage / Davis-Bacon / union basis matches the labour rate in the estimate.
  • Cash allowances and owner allowances carried exactly as the bid form defines them — no double-count, no omission.
  • Quote validity vs bid validity: will your gear and fixture prices survive award? Escalation clause if not.
  • Long-lead gear (switchgear, generators, transformers): lead times checked against the schedule; early-release noted.

5 · Quotes & math

  • Every sub/vendor quote: exclusions read line by line against YOUR scope — their exclusion is your carry.
  • Canadian projects: gear certified CSA / cULus / cETLus — US-only listings flagged.
  • Labour sanity pass: conduit hrs/ft, devices, terminations against your benchmarks — anything 2x off gets a second look.
  • Summary math re-added cold, once, by someone (or something) that didn't build the estimate.
  • Qualifications and exclusions letter attached — everything ambiguous above is either carried, RFI'd, or qualified.

When the package is too big for a checklist.

Bidprobe runs this pass automatically against your actual tender documents — findings with evidence and cost ranges, in minutes. See a complete sample report. Your first review is free.