Plain answer

What should electrical general conditions include?

Every job cost that isn't installed work: supervision, vehicles, small tools and consumables, temporary facilities, lifts and hoisting, permits and inspections, testing, closeout documents, cleanup, and travel. Price them from the schedule, because most of them cost money for every week you're on site, and read Division 1 for the ones the specs add.

What to read first in a bid packageSee a sample report

What to carry

Price them from the schedule

Most general conditions are time-based: a foreman, a truck or a lift costs money every week you're on site, whether you're installing or waiting. Take the duration from the bid documents or the GC's schedule, and say in your clarifications what duration your price assumes.

Questions estimators ask

Should general conditions be a percentage of the job?
A percentage is a quick check, but it hides the items that change with the schedule. Price them line by line from the duration, then compare with your usual percentage.
What happens if the job runs long?
Time-based general conditions grow with it. That's why your proposal should state the duration you priced, so extra time caused by others can be claimed.
How does Bidprobe help?
The review reads the Division 0 and 1 requirements with the rest of the package, and flags the ones that cost money, such as wage requirements, each tied to the page it came from.

Find the Division 1 costs before you price.